Thursday, June 16, 2011

10 kW Wind Turbine Running Again

After 4 months and 4 days of downtime due to 2 blown 6 kW Power One inverters, we're back up and running today.

Add to that the 2 months it was down in 2010, and that adds up to 25 per cent downtime in two years.


Paul Wende, Energy West, installs the two new Aurora 6 kW inverters
And the problem?

"A loose bolt on the heat dump," says Paul.

In the Roses and Thorns department,  a bouquet of Thorns to Power One in California for the horrendously slow response from their Customer Service department.  After more than 3 months of back and forth--with no decisions forthcoming on inverter failure and replacement--Paul contacted the Vice President of the company.  Obviously the VP had the authority to make the decision, whereas others did not.